This is the second annual status report on the progress of the Chapter's stream improvement efforts at Big Spring Creek, our adopted stream, near Leesburg, VA. Last year's report described the results of the 3 major work days held during the first half of 2002, following our signing an agreement with 2 landowners on February 24, 2002 whereby we agreed to rehabilitate the stream and the landowners agreed to permit a program of limited, managed catch-and-release fly fishing. To date both parties have scrupulously carried out the pledges to which they agreed.
(a). On November 16, 2002 a work day was held for the purpose of planting trees. The 15 volunteers from the Chapter who were on hand planted 122 trees, of which 36 were the larger balled-and-burlap type. The principal landowner paid about 2/3 of the cost of the trees, and the Chapter paid 1/3. This event was the subject of an article in the Loudoun Times Mirror newspaper.
(b). Because of the snow melt and extraordinarily heavy spring rains and resulting flooding, no work days were held during the first half of 2003. The first work day of our second year at the Creek took place on July 12, 2003. At that time, 25 volunteers continued the Chapter's earlier efforts to reduce erosion and limit sedimentation by pulling back and stabilizing stream banks which threatened to collapse, installing cedar revetments, and constructing a large hay bale gabion. We continued our earlier practice of using these "soft" engineering techniques rather than introducing rebar, cement erosion control devices such as "A-Jacks", and other more intrusive materials. A benthic macroinvertebrate monitoring survey conducted that day revealed the presence of various insect larvae which are intolerant of pollution and are only found in clean waters.
(c). Our second major work day was held on November 1, 2003. A total of 20 volunteers from the Chapter graded, matted, and planted a long 250' section of impaired bank and other shorter sections as well. Cedar revetments were installed and a rock vane deflector was built to relocate the flow away from a threatened bank.
(d). The third major work day of the year took place on November 18, 2003. The principal focus was on planting. Twenty-one volunteers participated. The group planted a total of 576 small "live stake" trees, with most placed between the flood plain and the water's edge in order to reinforce and stabilize the banks. The volunteers also installed a cedar revetment, planted grass, and relocated the left-over construction materials up a hillside, so that they would not be damaged in case of winter flooding.
(e). It should also be pointed out that volunteers from other organizations participated on these work days in addition to those from our Chapter. The VA Department of Forestry, Department of Game and Inland Fisheries, Loudoun Wildlife Conservancy, and Adams County (PA) TU also worked alongside our Chapter members.
(a). Embrace-A-Stream Grant. We have submitted a proposal to national TU for a one-to-one matching grant under the Embrace-A-Stream program to cover the expenses of materials and services at one full Saturday and one half weekday work day in early 2004. These two days efforts should complete all major work on our adopted stream, from the Route 15 bridge to the Spring Creek Lane bridge. Subsequently, our work there is expected to be largely limited to structure maintenance only.
(b). Corporate Support. Our Financial Resources committee has prepared a Power Point presentation to take to business and corporate sponsors for solicitation of donations in support of this and other stream projects, our youth programs, and other Chapter activities. We hope to begin meeting with our first business and corporate representatives in the early spring.<
(a). Depending upon the volume of winter and spring rains, we intend to try to schedule the first full work day of 2004 in early March, before the state-sanctioned moratorium takes effect which prohibits work in rainbow trout streams during the period March 15 - May 15. If our half day planting day cannot be undertaken in early spring, after the full work day, it will probably not take place until October or November, and that would be unfortunate.
(b). When our 3-year agreement expires at the end of 2005, our preference is to replace it with a new permanent agreement with no terminal date. If this idea is more than the landowners can comfortably accept, we intend to try to initiate a new long-term agreement covering a minimum period of 3 to 5 years.
(c). When the major work on the adopted area is completed in 2004, our plan is to investigate how to proceed towards successfully adopting from the Homeowners' Association the next stream segment downstream, between Spring Creek Lane and Twin Maple Lane. We fully recognize that negotiating with a disparate group of homeowners may be far more complex than dealing with only two landowners, with both interested in improving the stream, but it seems worthwhile to make our most determined effort.